Essential Main Sequence:
|
|
Simultaneous Odd Jobs:
|
|
String across deck w/2x4 blocks (to address any truss problems)
|
|
Sweep the deck
|
|
Erect exterior wall partitions
|
|
Insulate the tub/shower wall
|
|
Start building rakes
|
|
Foundation back filling (if necessary)
|
|
Start building small trusses
|
|
Carry and distribute wall sheathing (from pile to wall location)
|
|
Erect interior wall partitions
|
|
Install #16 nail holders at block under studs for exterior sheathing
|
|
2x8 double porch beams installed
|
|
Quality controlled exterior wall nailing
|
|
String and straighten long walls
|
|
Mark all door jambs for size and swing
|
|
Start exterior wall sheathing
|
|
Cut bottom plates of doors and closet
|
|
Install top plates on exterior and interior walls
|
|
Build attic saddles for plywood deck
|
|
Critical marking for trusses on top plates (no truss over plumbing wall; watch attic stairs & fan spacing)
|
|
Make sheathing 'A' frame lifting device
|
|
String across top plates and center partition, anticipate trusses
|
|
Storage room sheathing using OSB
|
|
Prepare trusses for first truss (exterior & interior)
|
|
|
|
Mark 1x3 on 24" centers for truss ties
|
|
|
|
Prepare & install pic board & braces
|
|
|
|
First truss up and braced from inside
|
|
|
|
Start gable end sheathing
|
|
|